Hi folks,
I'm just a little confuse on how exactly Performance % Complete behaves when it rolls up.
I have all my activities resource and cost loaded but it doesn't rollup. Below are my current settings:
Calculations Tab: $1
WBS Earned Value: Activity Percent Complete
Advance Scheduling: enabled recalculate assignment
Group & Sort: show total
Any help would be very much appreciated.
thanks.
Don
Hi Don,
Have you assigned already a budgeted cost to your activities? and what type of activity % complete you assigned? if you didnt assign any cost to any of your activities then theres nothing to be rolled up. also, if theres no percent progress in your assigned activity % complete still not rolled up. investigate this two things by showing in your windows column the budgeted cost, performance %complete, and activity % complete type that you used.
jash