UPDATING THE PROGRESS

A
AB Timo 👤 Member for 14 years 11 months

HI Gentlemen,

I have been updating the progress in primavers  version 6, by using Duration as % complete type.But i have also heard that one should use Physical as % complete type...I then used physical but the results were the same.Can someone tell me that what is the difference in using these two?????

 

Regards,

H
Hilal Hallani 👤 Member for 14 years 7 months

Physical % complete is entered by the user and it implies that when percent complete would not be an accurate measure of real work performed or remaining. Where % complete can be entered by the user or the programme, this is not a real measure.

Physical % complete is preferred over % complete in construction projects where speed of doing the work in activities does not remain same during the activity duration.

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts