HI Gentlemen,
I have been updating the progress in primavers version 6, by using Duration as % complete type.But i have also heard that one should use Physical as % complete type...I then used physical but the results were the same.Can someone tell me that what is the difference in using these two?????
Regards,
Physical % complete is entered by the user and it implies that when percent complete would not be an accurate measure of real work performed or remaining. Where % complete can be entered by the user or the programme, this is not a real measure.
Physical % complete is preferred over % complete in construction projects where speed of doing the work in activities does not remain same during the activity duration.