People working in primavera must know that when you schedule your programe of work after adding relationships,it makes its own critical path based on the longest path having 0 float...
Now I have a schedule with a critical path and i want to change my critical path.I know you can change it if you know how to play with the activity relationships ,but is there any other method that is time saving and shorter then the above mentioned one?????????????????????
Regards
Engr.Faiz
I got it...thank you
There are 4 ways to change you critical path:
1) Ammend the rules defining what is critical (schedule, options)
2) Change the relationships
3) Change the durations
4) Change the constraints
You shouldn't be looking for the quickest method, but the one which gives you the most realistic schedule.