Establishing a Critical Path

A
AB Timo 👤 Member for 15 years

Hi,

People working in primavera must know that when you schedule your programe of work after adding relationships,it makes its own critical path based on the longest path having 0 float...

Now I have a schedule with a critical path and i want to change my critical path.I know you can change it if you know how to play with the activity relationships ,but is there any other method that is time saving and shorter then the above mentioned one?????????????????????

Regards

Engr.Faiz

G
Gary Whitehead 👤 Member for 17 years 3 months

There are 4 ways to change you critical path:

1) Ammend the rules defining what is critical (schedule, options)

2) Change the relationships

3) Change the durations

4) Change the constraints

 

You shouldn't be looking for the quickest method, but the one which gives you the most realistic schedule.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts