Establishing a Critical Path

A
AB Timo 👤 Member for 14 years 11 months

Hi,

People working in primavera must know that when you schedule your programe of work after adding relationships,it makes its own critical path based on the longest path having 0 float...

Now I have a schedule with a critical path and i want to change my critical path.I know you can change it if you know how to play with the activity relationships ,but is there any other method that is time saving and shorter then the above mentioned one?????????????????????

Regards

Engr.Faiz

G
Gary Whitehead 👤 Member for 17 years 2 months

There are 4 ways to change you critical path:

1) Ammend the rules defining what is critical (schedule, options)

2) Change the relationships

3) Change the durations

4) Change the constraints

 

You shouldn't be looking for the quickest method, but the one which gives you the most realistic schedule.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts