Hi to all
Can we give the relation for different resources for any activity as we do in activity.
for example if we assign two different resources 1. Engineer and 2nd Draftmen. can we give the relation so that Draftmen will start work after Engineer work finish.Please guide me
Thanks for support in advance
KBJ
Can we create relationship in Resouces
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Primavera can't do that, nor can MS Project. Spider may, and I'm not sure about Asta.
But why don't you just have a seperate activity per resource?
Also, please don't post the same question in multiple forums. I have deleted the copies.
Cheers,
G