Clause 14 Program

Hi planners,

Why the Program of Work (construction schedule) is called "Clause 14 Program" while this is not clause 14, its clause 8.3. Also Recovery program is known as clause 14.2

Cheers - Tanveer

D
Daniel Limson 👤 Member for 24 years 8 months

In Europe and Middle East Countries, where Fidic Contracts are widely used, they normally refer to Clause 14 when it comes to programme issues and programme requirements, However, this is not applicable to East Asia or USA.

regards,

Daniel

F
Ferdinand U. 👤 Member for 18 years 11 months

Originally came from old FIDIC '87 and reprinted 92, Programme related at Clause 14

Now,from FIDIC '99, Programme clause changed to Clause 8

but most contracts still adapt the 87/92 COC 

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts