Clause 14 Program

Hi planners,

Why the Program of Work (construction schedule) is called "Clause 14 Program" while this is not clause 14, its clause 8.3. Also Recovery program is known as clause 14.2

Cheers - Tanveer

D
Daniel Limson 👤 Member for 24 years 7 months

In Europe and Middle East Countries, where Fidic Contracts are widely used, they normally refer to Clause 14 when it comes to programme issues and programme requirements, However, this is not applicable to East Asia or USA.

regards,

Daniel

F
Ferdinand U. 👤 Member for 18 years 10 months

Originally came from old FIDIC '87 and reprinted 92, Programme related at Clause 14

Now,from FIDIC '99, Programme clause changed to Clause 8

but most contracts still adapt the 87/92 COC 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts