Hi planners,
Why the Program of Work (construction schedule) is called "Clause 14 Program" while this is not clause 14, its clause 8.3. Also Recovery program is known as clause 14.2
Cheers - Tanveer
Hi planners,
Why the Program of Work (construction schedule) is called "Clause 14 Program" while this is not clause 14, its clause 8.3. Also Recovery program is known as clause 14.2
Cheers - Tanveer
In Europe and Middle East Countries, where Fidic Contracts are widely used, they normally refer to Clause 14 when it comes to programme issues and programme requirements, However, this is not applicable to East Asia or USA.
regards,
Daniel
Originally came from old FIDIC '87 and reprinted 92, Programme related at Clause 14
Now,from FIDIC '99, Programme clause changed to Clause 8
but most contracts still adapt the 87/92 COC