Baseline dates

M
Manoj VS 👤 Member for 16 years 11 months

Hai,

Is there any chance to change start / end date of base line in P6

When I assigned a baseline start date / end date shown different.

Can anybody advice me?

Thanks in advance

S
Shah. HB 👤 Member for 17 years 6 months

Hi

you can change the baseline to meet the project requirement after incorporating ,make sure you first maintain baseline and then assign baseline to respective project

R
Raymund de Laza 👤 Member for 16 years 6 months

Manoj,

Seems you assigned a baseline which is the current project and not the baseline project you added.

Check if you added a baseline project

>>> Project>>>Manage Baseline

>>>Assign Baseline>>select the right baseline you added

 

Hope this will solve your problem.

Regards,

D
Dieter Wambach 👤 Member for 19 years 4 months

Manoj

It depends on what you want to modify. Projects--> Maintain BL:

- You can update a BL with current values.

- You can restore --> modify --> (re-)assign.

With intention this needs a certain security level.

Regards

Dieter

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts