Hai,
Is there any chance to change start / end date of base line in P6
When I assigned a baseline start date / end date shown different.
Can anybody advice me?
Thanks in advance
Hai,
Is there any chance to change start / end date of base line in P6
When I assigned a baseline start date / end date shown different.
Can anybody advice me?
Thanks in advance
Hi
you can change the baseline to meet the project requirement after incorporating ,make sure you first maintain baseline and then assign baseline to respective project
Manoj,
Seems you assigned a baseline which is the current project and not the baseline project you added.
Check if you added a baseline project
>>> Project>>>Manage Baseline
>>>Assign Baseline>>select the right baseline you added
Hope this will solve your problem.
Regards,
Manoj
It depends on what you want to modify. Projects--> Maintain BL:
- You can update a BL with current values.
- You can restore --> modify --> (re-)assign.
With intention this needs a certain security level.
Regards
Dieter