Can Any body provide me the difference between , Programme revision,recovery , Update ,, is it mentioned any where
in the PMI Books
Can Any body provide me the difference between , Programme revision,recovery , Update ,, is it mentioned any where
in the PMI Books
Hi,
If your project got extension of time due to delays (by either parties), then, you will prepare revised programme/schedule.
If your project got delayed and client is not agreeing for extension of time, then, you need to prepare & submit Recovery Program / schedule in order to recover/compensate your delays.
Bi-weekly / Monthly progress updation in your schedule by putting actual dates & pecentage complete is your programme update.
Regards,
Rizwan Rauf