Can Any body provide me  the difference between , Programme revision,recovery , Update ,, is it mentioned any where

in the PMI Books

R
Rizwan Rauf, PMP 👤 Member for 17 years

Hi,

If your project got extension of time due to delays (by either parties), then, you will prepare revised programme/schedule.

If your project got delayed and client is not agreeing for extension of time, then, you need to prepare & submit Recovery Program / schedule in order to recover/compensate your delays.

Bi-weekly / Monthly progress updation in your schedule by putting actual dates & pecentage complete  is your programme update.

 

Regards,

 

Rizwan Rauf