Revise,recover & Update

H
Hatem Smadi 👤 Member for 15 years 7 months

Can Any body provide me  the difference between , Programme revision,recovery , Update ,, is it mentioned any where

in the PMI Books

R
Rizwan Rauf, PMP 👤 Member for 16 years 11 months

Hi,

If your project got extension of time due to delays (by either parties), then, you will prepare revised programme/schedule.

If your project got delayed and client is not agreeing for extension of time, then, you need to prepare & submit Recovery Program / schedule in order to recover/compensate your delays.

Bi-weekly / Monthly progress updation in your schedule by putting actual dates & pecentage complete  is your programme update.

 

Regards,

 

Rizwan Rauf

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts