URGENT!!!
Dear All,
I 'm facing a problem with clander like;
One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.
Regards,
maqeel
([email protected])+966599981584
P6 is not a day-oriented CPM software. Activities are scheduled down to the minute. To understand your issue, you will need to display hours and minutes as well as days. Once you do, I am sure that the answer to your problem will be evident. Good luck!