One (1) day Calendar Issue

URGENT!!!

Dear All,

I 'm facing a problem with clander like;

One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration  But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.

Regards,

maqeel

([email protected])+966599981584

R
Ronald Winter 👤 Member for 23 years 5 months

P6 is not a day-oriented CPM software.  Activities are scheduled down to the minute.  To understand your issue, you will need to display hours and minutes as well as days.  Once you do, I am sure that the answer to your problem will be evident.  Good luck! 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts