Eanred Value rules for M&E procurement

S
Shah. HB 👤 Member for 17 years 7 months

Hi Gray



I have come across a case in which the specification states that delivery of materials Eg,-Generator ,at site cost 75% of Budgeted Value and remaining 25 % goes to the respective installation Activities

S
Shah. HB 👤 Member for 17 years 7 months

Hi Gray



Are u looking for Earned Value procedure in MEP or WBS in developing the MEP Baseline schedule

G
Gary Whitehead 👤 Member for 17 years 3 months

I’m looking for how you apportion the budget cost & assocaited earned value of major M&E kit in your baseline programme



e.g. perhaps 10% of the value is earned when the order is placed, 50% throughout manufacturing period, 10% at FAT and 30% on delivery

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts