Hi Shazia
As Rodel says - it is the logic that drives the critical path.
If the logic is correct then you should not try to adjust it to give false criticality to a particular task.
As a side issue tasks of 90 to 1`50 days are far too long - maxmum task duration should be 10 days.
Best regards
Mike Testro
Dear Sir.
Thanks so much for your kind reply.
I understood now ,
Best Regards
Shazia,
Longest Path doesnt mean longest activity. It is the longest network created by the logic behind it.
If the longest activity is not critical it means that activity is not sitting on critical path and or longest path of the network. If you want it to be critical then check the logic and make sure it sit on the critical path and or total float = 0.