Longest Path Critical Activities
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Shazia
As Rodel says - it is the logic that drives the critical path.
If the logic is correct then you should not try to adjust it to give false criticality to a particular task.
As a side issue tasks of 90 to 1`50 days are far too long - maxmum task duration should be 10 days.
Best regards
Mike Testro
Dear Sir.
Thanks so much for your kind reply.
I understood now ,
Best Regards
Shazia,
Longest Path doesnt mean longest activity. It is the longest network created by the logic behind it.
If the longest activity is not critical it means that activity is not sitting on critical path and or longest path of the network. If you want it to be critical then check the logic and make sure it sit on the critical path and or total float = 0.