Change Order Claims

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Rizwan,



I would recommend that you start immediately by making a list of all the Change Order and notifying the Client of them.



Then you start collecting the data for each Change Order.



I would recommend that you make "As Built" drawings and put the necessary Engineers to calculate the differences between the "Issued For Construction" drawings and the "As Built Drawings". This way you will have evidence of the chances and by doing a simple quantity surveying you can find the quantities (hopefully).



You can submit estimates of the cost based on good Contacting Practices and BOQ prices. This will be negotiated with the client.



With kind regards,



Samer

M
Mike Testro 👤 Member for 20 years 5 months

Hi Rizwan



It is not a good idea to disclose the companies name in an open forum - you might be disclosing confidential information.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts