Dear Rizwan,
I would recommend that you start immediately by making a list of all the Change Order and notifying the Client of them.
Then you start collecting the data for each Change Order.
I would recommend that you make "As Built" drawings and put the necessary Engineers to calculate the differences between the "Issued For Construction" drawings and the "As Built Drawings". This way you will have evidence of the chances and by doing a simple quantity surveying you can find the quantities (hopefully).
You can submit estimates of the cost based on good Contacting Practices and BOQ prices. This will be negotiated with the client.
With kind regards,
Samer
Hi Rizwan
It is not a good idea to disclose the companies name in an open forum - you might be disclosing confidential information.
Best regards
Mike Testro