Programme for Water and Wastewater treatment plant

L
Lucas l 👤 Member for 16 years 2 months
G
Gary Whitehead 👤 Member for 17 years 2 months

Lucas,



I assume this is a new build, not extension of existing facilities?



For waste water, some other things to watch out for are:



-Is Odour Control required? If so, it may be that this must be commissioned before wet commissioning of the process stream(s) begins.



-How will the final sludge be processed? If by digestion then you may have to allow for working near dangerous gases (hot work permits, specialist operators, etc)



-For commissioning, some of the process units may require initial ’seeding’ with activated sludge. Depending on size and design of the plant, these can be considerable quantities.



-special piling techniques may be required to ensure no contamination of below-ground aquifers

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Lucas,



Your Milestone Schedule can be:



I. Material Submittals.

II. Shop Drawings Submittals.

III. Procurement of Equipment

IV. Construction

1. Excavation

2. Blinding

3. Foundation

4. Walls and Diaphrams

5. Treatment/Insulation/Insulation protection of Walls from outside

6. Fill in layers around the structure

7. Slab of Equipment Room

8. Finishes of Equipment Room

9. MEP

10. Landscape works

11. Handing over



V. Testing & Commissioning (this is done when you have sludge ready in the system)



With kind regards,



Samer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts