Schedule for Road Utilities
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Pacifico,
there are some typical activities for your reference.
1. ELS Design Submission & Approval
2. Temp. Traffic Arrangement Submission & Approval
3. Design submission & Approval by Utility Undertakers
4. Excavation Permit Application & Approval
5. Trial pits
6. TTA Implementation
7. ELS & Excavation
8. Existing Utilities Diversion / cut-off
9. Relocation of Utilities
10. Backfilling & Reinstatement
11. Repeat steps 6 to 10 if more than one TTA stage.
Regards,
KS