Schedule for Road Utilities

K
KS Wong 👤 Member for 18 years 9 months

Hi Pacifico,



there are some typical activities for your reference.



1. ELS Design Submission & Approval

2. Temp. Traffic Arrangement Submission & Approval

3. Design submission & Approval by Utility Undertakers

4. Excavation Permit Application & Approval

5. Trial pits

6. TTA Implementation

7. ELS & Excavation

8. Existing Utilities Diversion / cut-off

9. Relocation of Utilities

10. Backfilling & Reinstatement

11. Repeat steps 6 to 10 if more than one TTA stage.



Regards,

KS