Hi Pacifico,
there are some typical activities for your reference.
1. ELS Design Submission & Approval
2. Temp. Traffic Arrangement Submission & Approval
3. Design submission & Approval by Utility Undertakers
4. Excavation Permit Application & Approval
5. Trial pits
6. TTA Implementation
7. ELS & Excavation
8. Existing Utilities Diversion / cut-off
9. Relocation of Utilities
10. Backfilling & Reinstatement
11. Repeat steps 6 to 10 if more than one TTA stage.
Regards,
KS