Small Project

A
Azeem Abdul 👤 Member for 17 years 7 months
S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Maask,



Before you determine the duration, you need to assign the resources; manpower, material and equipment. Depending on the productivity rates, you will determine the duration.



You will need to talk to your team members for determining the available resources.



Best,



SAmer

A
Ahmed Khan 👤 Member for 17 years 7 months

Thank U very much samer,



Could U Plz forward me in detailed with the durations of activities.?



Regards



Maask

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Azeem,



The activities are:



1. Excavation

2. Blinding

3. Shuttering for Foundation

4. Reinforcement for Foundation

5. Concreting foundation

6. Reinforcement Vertical Elements (20 columns)

7. Shuttering vertical Elements

8. Concreting vertical Element

8.1 Insulation vertical Elements

9. Fill and compaction up to SOG

10. Blinding for SOG

11. Insulation for Slab on Grade

12. Reinforcement for Slab on Grade

13. Concreting of Slab on Grade

Repeat for each level: G+ L1, L2, L3

14. Reinforcement vertical Elements

15. Shuttering vertical elements

16. Concreting vertical elements

17. Deshuttering vertical elements

18. Shuttering for Slab

19. Reinforcement for Slab

20. Concreting slab.



These are the basic activities, you will need to fill in the blanks as per the Contract requirements.



Let us know if you need more assistance.



Best,



Samer

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts