i want to rate analysis of 2500mm dia pipe making with 20mm thickness Mild steel sheet. with material cost

A
Abhijit Kale 👤 Member for 18 years 10 months

Dear Anu,

The productivity depends upon the time cycle required for completing an activity.

time cycle depends upon, many factors,such as:

1.Diameter of Pipe.

2.Man power deployed

3.Equipemnt deployed.

4. Location and climateic conditions



you have given to little information in your querry.



At least mention the diameter of pipe.

cheers,

Abhi