ok got you.
SORRY...DEAR
I FORGET TO EXPLAIN YOU ..UDATE FILE NOT A BASE LINE..IT IS DUMMY OF BASLINE...WHICH I AM USE TO UPDATE....BY PRIMAVERA...
TO GET A PLANNED % PROGRESS AS ...I DID NOT MENTION COST OR....
CHEER
didnt get you sorry,
i can do the same in current project, as it is compared against the baseline, as i update current schedule, i get earned value for this in terms of units or cost?
why would i have to update baseline in order to get planned % progress.... are you talking about PLanned value? (budgted cost of work scheduled-BCWS)???
Please light more
Hi,Shahzad
This is the one way to obtained a Planned % Progress
based on duration.
I did this ...for my current project..which is very helpfull for Invoicess.
you are right this is only for P3.1 option.
I hope ..it would be clear...
Thanks
Shahzad
I dont really get you,,why press Ctrl + F9 ,,it never works anyway in P6/P5..
Why do you really need to updates the baseline,,,its a frozen entity, and you only reschedule current programme,,,
please explain to me what you are trying to say.
may be i am missing something?
thanks
TC