BEST TO UPDATE

S
Shahzad Ahmad 👤 Member for 18 years 3 months

SORRY...DEAR



I FORGET TO EXPLAIN YOU ..UDATE FILE NOT A BASE LINE..IT IS DUMMY OF BASLINE...WHICH I AM USE TO UPDATE....BY PRIMAVERA...



TO GET A PLANNED % PROGRESS AS ...I DID NOT MENTION COST OR....



CHEER


S
Shahzad Sikandar 👤 Member for 20 years 4 months

didnt get you sorry,



i can do the same in current project, as it is compared against the baseline, as i update current schedule, i get earned value for this in terms of units or cost?



why would i have to update baseline in order to get planned % progress.... are you talking about PLanned value? (budgted cost of work scheduled-BCWS)???



Please light more

S
Shahzad Ahmad 👤 Member for 18 years 3 months

Hi,Shahzad







This is the one way to obtained a Planned % Progress



based on duration.



I did this ...for my current project..which is very helpfull for Invoicess.



you are right this is only for P3.1 option.



I hope ..it would be clear...



Thanks

S
Shahzad Sikandar 👤 Member for 20 years 4 months

Shahzad



I dont really get you,,why press Ctrl + F9 ,,it never works anyway in P6/P5..



Why do you really need to updates the baseline,,,its a frozen entity, and you only reschedule current programme,,,



please explain to me what you are trying to say.



may be i am missing something?



thanks

TC

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts