P5 to P3 Converstion
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi all,
Whenever i am exporting a schedule from P3 to P5 , i got negative float in P5 however there was no negative float in P3 for the same schedule.
Pls advise.
Thanks
Mohd
hi all planners
the site for downloading the P5 manual is not working or damaged
if any one know another like
please advise
I got it fixed.
Has to do with un-checking the Primary Resourse box on each item under the Resources tab on the Activity View.
Did a global change to effect all activities.
Brian
Negative lag is on the relationships. Which kinds of relationships are involved? How was the lag before?
If the float becomes negative you can check the calendars.
Cheers
Dieter