labor inefficiencies on the account of heat

W
William Sargent 👤 Member for 19 years 4 months

Thanks to everyone who posted a reply on this thread!



I really like this site and everyone seems not only helpful but knowledgable, too.



I found my answer using the National Electical Contractors Association’s "The Effect of Temperature on Productivity" published in 1974 to extrapulate the intel that I needed.



If anyone is looking for more info, look here:



http://www.necanet.org/store/index.cfm?fuseaction=search_results_sites&…



The Effect of Temperature on Productivity

Published: 2004

Description:

The effects of extreme combinations of temperature and humidity on electrical labor productivity are identified. The results are presented in a series of tables and charts, which provide a powerful tool that can be used by contractors to adjust their bids during the bidding process and to support requests for time extensions and compensation during the construction process. To purchase this study along with the other six studies that comprise this entire report, see Index No. 5079CK - Productivity: Quantifying the Impacts of Adverse Working Conditions on Electrical Construction (Productivity Studies Kit).

View Related files (Note: these are in PDF format)

Table of Contents



Index Number:

5072-04 Format:



Thanks again!



Very Respectfully,


A
Anoon Iimos 👤 Member for 19 years 8 months

in some areas, it goes up to 53 degrees celcius, from around 8:00 am to 4:00 pm, people cannot work continuously for an hour if the work is outdoor, if it’s indoor, you’ll need air, at least provide them with a fan.



but in my case, oh it’s very cold in here...

I
Ife Olyke 👤 Member for 19 years 4 months

William,



It is evident that extreme heat impacts on the productivity of your labour. My opinion: depending on your planning unit, you can adjust your calendar to capture this impact. Consider this scenario:



Temperature: 110 degrees Fahrenheit

Activity: laying of bricks

Budgeted quantity BQ: 100 hours

Number of men: 2 per shift

Shift: 2 shifts @ 12 hours per shift



Assuming that the BQ is not under estimated or over estimated, if the work force is 100% productive, then the original duration should be 50 hours. For argument sake, I want to assume that the productivity of the work force under extreme heat is 60%. You can adjust your calendar for the period (months) of the shut down to compensate the effect of the heat by selecting non work hours approximately 5 hours per shift. Your original duration is still 50 hrs, but your calendar will have 7 productive hrs to do the job per shift. This makes your bars longer. I hope this makes sense.



Cheers



Ifeanyi

C
Chris Oggham 👤 Member for 22 years

Hi William,



I can’t help you too much here I’m afraid, but you might get a bit of useful information from this thread on the forum. If you need more detail, click on the envelope icon next to any of the names, you’ll then be able to send a private message to that person and can ask them for more detail.



Chris Oggham

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts