High rise building schedule

A
Andrew Pearce 👤 Member for 25 years

Requirement for concrete pumps is derived from quantity of concrete to be placed divided by out put from pump.



Requirement for tower cranes is similar, calculate number of lifts required (number of table forms, bundles of rebar etc) make an estimate of how many lifts can be made in a day.



Divide total number of lifts per day by number of lifts per crane = number of cranes required. Note at some stage you need to make allowance for crane downtime due to maintenance and high winds,

M
Mohammed Shafiq 👤 Member for 19 years 4 months

Who are you working for?



I have worked in Dubai and Abu Dhabi.



I too would be interested to know the answer to your question. Never planned a high rise building before.



What’s it like planning for the oil & gas sector? What jobs have you worked on in the oil & gas industry?


Forum Sponsor

Top Posters

ahmad rashidi
4 posts
paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts