Requirement for concrete pumps is derived from quantity of concrete to be placed divided by out put from pump.
Requirement for tower cranes is similar, calculate number of lifts required (number of table forms, bundles of rebar etc) make an estimate of how many lifts can be made in a day.
Divide total number of lifts per day by number of lifts per crane = number of cranes required. Note at some stage you need to make allowance for crane downtime due to maintenance and high winds,
Who are you working for?
I have worked in Dubai and Abu Dhabi.
I too would be interested to know the answer to your question. Never planned a high rise building before.
Whats it like planning for the oil & gas sector? What jobs have you worked on in the oil & gas industry?