Linear and non-linear ativities on the same network

A
Alex Wong 👤 Member for 23 years 4 months

Ronnie



you are right, you can plan your network in both linear and non linear.



However, that is only the plan, in progress update you progress your activity base on actual completion.



In activity progress you have a few choice,

1. Duration

2. Physical

3. 0/100

4. 50/100

5. Weighted

6. Cost (Acutal)



you need to work out the method prior to approval of your schedule



Regards



Al

R
Ronald Romero 👤 Member for 19 years 7 months

Angus,



You can make it linear on nonlinear as it suits you. Just define the resource curve you want tto use to progress your activities.



Try it and in few runs you can have the progress your client want.



Cheers,



Ronnie

E
Edgar Ariete 👤 Member for 20 years 11 months

Angus,



It’s basically linear, so you have to break it down into smallest possible detail to make it realistic.

J
James Griffiths 👤 Member for 20 years 1 month

Hi Angus,



Clarification please on what your client means by linear and non-linear progress. I’m making the assumption that non-linear means that the activity stops-and-starts....but I could be wrong.



Cheers.



James.

Forum Sponsor

Top Posters

Iftikhar Awan P.Eng.
19 posts
ahmad rashidi
4 posts
paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts