Linear and non-linear ativities on the same network
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Ronnie
you are right, you can plan your network in both linear and non linear.
However, that is only the plan, in progress update you progress your activity base on actual completion.
In activity progress you have a few choice,
1. Duration
2. Physical
3. 0/100
4. 50/100
5. Weighted
6. Cost (Acutal)
you need to work out the method prior to approval of your schedule
Regards
Al
Angus,
You can make it linear on nonlinear as it suits you. Just define the resource curve you want tto use to progress your activities.
Try it and in few runs you can have the progress your client want.
Cheers,
Ronnie
Angus,
Its basically linear, so you have to break it down into smallest possible detail to make it realistic.
Hi Angus,
Clarification please on what your client means by linear and non-linear progress. Im making the assumption that non-linear means that the activity stops-and-starts....but I could be wrong.
Cheers.
James.