Alex that is great thanks for your help.
Rgds
Sofia
hmmm... first workshop on the project
since you already have the PBS (WBS)
I suggest the following
Base on the PBS
Topic - Result
Role & Responsibility - R&R Matrix
Deliverable - Deliverable List with R&R
Duration Estimation - (Need to be discuss individually in separate meeting)
Key milestone dates - Deliverable List with Milestone
Risk & Contingency - Risk & Treatment Plan
Reporting Cycle - Progress Report Timetable
Depend on the size of the project this workshop will run at least 3-4 hrs min
HTH
Alex