Advise for Running a Planning Workshop

S
Sofia Frost 👤 Member for 19 years 5 months
A
Alex Wong 👤 Member for 23 years 4 months

hmmm... first workshop on the project



since you already have the PBS (WBS)



I suggest the following

Base on the PBS

Topic - Result

Role & Responsibility - R&R Matrix

Deliverable - Deliverable List with R&R

Duration Estimation - (Need to be discuss individually in separate meeting)

Key milestone dates - Deliverable List with Milestone

Risk & Contingency - Risk & Treatment Plan

Reporting Cycle - Progress Report Timetable



Depend on the size of the project this workshop will run at least 3-4 hrs min



HTH



Alex