Excelent sugestion!
Do not know why I never thought of this? Yes it works well, thanks alot Vladimir. Sometimes the simplist things are overlooked.
What I have done so this process is not forgotten is added it as the only resource to level automatically after scheduling.
Thanks Again.
One of potential solutions:
1. Create some dummy resource A with 100 total quantity.
2. Assign 1 unit (or less but more than zero) of this resource to all activities except Commissioning activity.
3. Assign 100 units of this resource to Commissioning.
4. Level your project.
Inform me if the problem is solved.
Best Regards,
Vladimir