Scheduling work around an activitity

N
Nigel Hussey 👤 Member for 20 years 1 month

Excelent sugestion!



Do not know why I never thought of this? Yes it works well, thanks alot Vladimir. Sometimes the simplist things are overlooked.



What I have done so this process is not forgotten is added it as the only resource to level automatically after scheduling.



Thanks Again.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

One of potential solutions:

1. Create some dummy resource A with 100 total quantity.

2. Assign 1 unit (or less but more than zero) of this resource to all activities except Commissioning activity.

3. Assign 100 units of this resource to Commissioning.

4. Level your project.



Inform me if the problem is solved.



Best Regards,

Vladimir

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts