Progress Updates on Resourced and Duration Based Plan

O
Omar Grant 👤 Member for 20 years 9 months

Hi Danya - just a comment on procurement weightings: I normally score a weighting of 75% when the PO/Contract awarded, 25% to the manufacture/delivery. Cheers,

D
Danya Pearce 👤 Member for 21 years 11 months

thanks,



appreciate your response. will try it!!!



All the best



Danya

S
Sukumaran Subaramaniyan 👤 Member for 21 years 4 months

Danya,



You can assign dummy resource to procurement schedule, i.e Man = 1. Then export the info to excel to calculate the weight and update the progress.



HTH.