thanks for the advice
Hi Danya - just a comment on procurement weightings: I normally score a weighting of 75% when the PO/Contract awarded, 25% to the manufacture/delivery. Cheers,
thanks,
appreciate your response. will try it!!!
All the best
Danya
Danya,
You can assign dummy resource to procurement schedule, i.e Man = 1. Then export the info to excel to calculate the weight and update the progress.
HTH.