Re-baselining W.I.P. Activities

R
Rob Green 👤 Member for 20 years 10 months
J
Joanne Foster 👤 Member for 22 years 5 months

Hi Rob



If the only reason for rebaselining in-progress is due to rate changes, then I do it...it takes a bit to check that the software has actually calculated things correctly though. I like to take a copy of the baseline and muck around with that one first, to make sure things will go smoothly.



Any other time, rebaselining in-progress is a bit of a no-no in my book, particularly in defence environment. So standard thing is to set BCWS = BCWP and replan the remainder...or set BCWS = BCWP = ACWP for a formal reprogramme.



Regards

Joanne

R
Raja Izat Raja Ibrahim 👤 Member for 21 years 1 month

Hi Rob,

as far i know If re-baseline the progress its does not impact the cost, its only have to shift remaining progress followed by the cost /resource, Unless there is additional activities to be add or labour rate changes (but not very frequent happened) cause there is contract to be followed.

Forum Sponsor

Top Posters

James Williams
74 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts