Re-baselining W.I.P. Activities
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Rob
If the only reason for rebaselining in-progress is due to rate changes, then I do it...it takes a bit to check that the software has actually calculated things correctly though. I like to take a copy of the baseline and muck around with that one first, to make sure things will go smoothly.
Any other time, rebaselining in-progress is a bit of a no-no in my book, particularly in defence environment. So standard thing is to set BCWS = BCWP and replan the remainder...or set BCWS = BCWP = ACWP for a formal reprogramme.
Regards
Joanne
Hi Rob,
as far i know If re-baseline the progress its does not impact the cost, its only have to shift remaining progress followed by the cost /resource, Unless there is additional activities to be add or labour rate changes (but not very frequent happened) cause there is contract to be followed.