Creating Target plan

A

I’ved run a check now on the Project Overview and its ok

and i check also format bar/modify then i didn’t noticed

that my start point is not in Target early start.



Thanks for your help.



Regards,

wilfred

M
MK TSE 👤 Member for 24 years 4 months

I can’t get it. Target bar always parallel to the currect bar except they are placed in same position. Please check the following: -

- Have target been assigned in Project overview

- What option been selected in bar format

A

Hi Guys,



In relation to Pelita’s question, I’ved done copying the project and make it as a target. But when i tried to show the target bar it appears to be not parallel with the current and it shows a long bar. Let say the project starts Jan 2004 and my activity starts May 2004 and end june the target bar shows Jan - June.



Need Help



Thanks,



wilfred

M
MK TSE 👤 Member for 24 years 4 months

Pelita,

Your method is to assign an Existing project as tartget and/or update the assigned target project by current open project. It is not for creating a project for target from current.



Use Moises’s method, you now have a copy. Then you part is the OK for assign. Or by File - Open - select the current project - click Overview button at bottom left, goto to page Targets, select a project for target assignment.

Z
Zq qz 👤 Member for 23 years 1 month

Hello Kabayan,

You can also this procedure. Go to the ff Menu



TOOLS>>>>PROJECT UTILITIES >>> COPY ( read in the manual how to copy ...)be sure that copy file and orig file on same folder, then you can use this as your Target.



Regards,






Forum Sponsor

Top Posters

pennyu
0 posts
James Williams
74 posts
jaasland
0 posts
Doron El
3 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts