Creating Target plan

F
Forum Guest 👤 Member for 17 years 5 months
L
Luca Basile 👤 Member for 23 years

As suggested before, copy the schedule.

Open the schedule you updtae. In the load form, go on "Overview", select the Target, and then You can put multiple target.

Let say first the baseline, then last update period.



When You open the program, in the bars management, must add the target bars (target 1 early start and finish) and in a different level(POS), fo example level 2.



The same for how amny target You added or You want to show.



Of course You can compare late dates on so on.

Z
Zq qz 👤 Member for 23 years 1 month

1st Method. >>> Go to TOOLS >> PROJECT UTILITIES >>> TARGET >> CREATE BY TYPING NAME OF PROJECT YOU WANT ....



2ND mETHOD : COPY YOUR ORIG PROJECT. THEN USE THIS AS TARGET.



You can also go to help for more info........


Forum Sponsor

Top Posters

pennyu
0 posts
James Williams
74 posts
jaasland
0 posts
Doron El
3 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts