Yes, it appears to be a duplicate thread. Im locking this one then. We do not need two threads for one subject.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Hope they are related.
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=3875
According to what pasted, I assume the software is P3.
Folks, the original question did not specify what software was being used. This forum is for general discussions and assumptions should be checked carefully.
Perhaps the original question was answered already?
http://www.planningplanet.com/forum/forum_post.asp?Cat=1&Top=2936
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
As suggested before, copy the schedule.
Open the schedule you updtae. In the load form, go on "Overview", select the Target, and then You can put multiple target.
Let say first the baseline, then last update period.
When You open the program, in the bars management, must add the target bars (target 1 early start and finish) and in a different level(POS), fo example level 2.
The same for how amny target You added or You want to show.
Of course You can compare late dates on so on.
1st Method. >>> Go to TOOLS >> PROJECT UTILITIES >>> TARGET >> CREATE BY TYPING NAME OF PROJECT YOU WANT ....
2ND mETHOD : COPY YOUR ORIG PROJECT. THEN USE THIS AS TARGET.
You can also go to help for more info........