SCHEDULE PERFORMANCE FACTOR

Z
Zq qz 👤 Member for 23 years
F
Forum Guest 👤 Member for 17 years 4 months

Ref. the post that SPI is 1. Yes planningwise but not arithmetically as the formula suggested because how can you have BCWP if the project have not started.

B
Bernard Ertl 👤 Member for 23 years 6 months

There are several ways to generate a curve of % complete targets. We graph the cumulative scheduled manhours from ES to EF. Ie. for day 1, total all scheduled manhours on day 1 and divide by the total manhours for the entire schedule. For Day 2, total all manhours for day 2, divide by the total manhours for the entire schedule and add day 1 percentage.



You can also graph the manhours from LS to LF in addition to the above to display a target range for each day (or whatever your reporting period is).



HTH!



Bernard Ertl

InterPlan Systems Inc. - Project Management Software, Project Planning Software

F
Forum Guest 👤 Member for 17 years 4 months

Sorry to be so contrite! but a baseline plan however good or bad assumes 100% efficiency throughout the life of the programme so whether you look at it weekly, monthly the performance index is constant - but it seems a meaningless question - I must be missing something.



However you can assess the risks associated using various techniques - Three-point-estimating is fairly reliable providing the project is not completely new to the organisation. This should give you the earliest/’mid’/latest dates for the project - I suppose you can then set these up as some sort of PPI.

F
Forum Guest 👤 Member for 17 years 4 months

erm the projected performance index at the start of a project is always 1.

Z
Zq qz 👤 Member for 23 years

Thank you Gentlemen,

But what I want to know is Projected Performance Index from start to finish of the project (i.e. weekly, monthly,etc... as in - projected %).

F
Forum Guest 👤 Member for 17 years 4 months

Moises,



Planned or Scheduled SPI is meaningless/no use at all at the start of the project because it will be 0. As you project it, it is also 0 because you don’t have a numerator(Actual Quantity).



Perhaps what you are asking is the projected %Complete using manhours.

M
Mehdi Rashidi Alangeh 👤 Member for 22 years 11 months

Please see websit PD-Trak FOR YOUR QUESTION.

PD-Trak™ provides key metrics to determine project, product, and portfolio performance

Z
Zq qz 👤 Member for 23 years

Forum Guest, thanks for your reply. But what i want to know is the schedule SPI, which i want to establish before project starts (i.e. weekly , monthly etc basis).

F
Forum Guest 👤 Member for 17 years 4 months

Moises,



Im not really sure about your question, but the following might be of help.



Using earned value analysis, just change the cost values to quantity values.



The SPI (schedule performance index) field shows the ratio of work performed to work scheduled (BCWP/BCWS). SPI is often used to estimate the project completion date.



How Calculated



SPI = BCWP / BCWS



An SPI ratio greater than 1 indicates that youre ahead of schedule. Likewise, an SPI ratio less than 1 indicates that youre behind schedule. For example, an SPI of 1.5 means that youve taken only 67% of the planned time to complete a portion of a task in a given time period. An SPI of 0.8 means that youve spent 25% more time on a task than was planned.



CPI (cost performance index) field shows the ratio of budgeted (or baseline) costs of work performed to actual costs of work performed, up to the project status date or todays date. Use quantity instead.



How Calculated CPI is the ratio of BCWP (budgeted cost of work performed) to ACWP (actual cost of work performed):



CPI = BCWP / ACWP



Best Uses This value indicates whether you are over or under budget as of the data date.












Z
Zq qz 👤 Member for 23 years

Gentlemen,

What i mean is Schedule Performance / productivity Factor / index (i.e. in terms of manhours). In determining the actual it is = earned manhour / Actual Manhour.



Regards

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts