Ref. the post that SPI is 1. Yes planningwise but not arithmetically as the formula suggested because how can you have BCWP if the project have not started.
Member for
22 years 11 months
Member for22 years11 months
Submitted by Bernard Ertl on Thu, 2003-11-20 08:59
There are several ways to generate a curve of % complete targets. We graph the cumulative scheduled manhours from ES to EF. Ie. for day 1, total all scheduled manhours on day 1 and divide by the total manhours for the entire schedule. For Day 2, total all manhours for day 2, divide by the total manhours for the entire schedule and add day 1 percentage.
You can also graph the manhours from LS to LF in addition to the above to display a target range for each day (or whatever your reporting period is).
Sorry to be so contrite! but a baseline plan however good or bad assumes 100% efficiency throughout the life of the programme so whether you look at it weekly, monthly the performance index is constant - but it seems a meaningless question - I must be missing something.
However you can assess the risks associated using various techniques - Three-point-estimating is fairly reliable providing the project is not completely new to the organisation. This should give you the earliest/’mid’/latest dates for the project - I suppose you can then set these up as some sort of PPI.
Planned or Scheduled SPI is meaningless/no use at all at the start of the project because it will be 0. As you project it, it is also 0 because you dont have a numerator(Actual Quantity).
Perhaps what you are asking is the projected %Complete using manhours.
Member for
22 years 11 months
Member for22 years11 months
Submitted by Bernard Ertl on Wed, 2003-11-19 11:09
Your last two posts are confusing to me. How can you determine a SPI based upon actual hours before the project starts? Perhaps I am still not understanding what you are trying to do....
Forum Guest, thanks for your reply. But what i want to know is the schedule SPI, which i want to establish before project starts (i.e. weekly , monthly etc basis).
Im not really sure about your question, but the following might be of help.
Using earned value analysis, just change the cost values to quantity values.
The SPI (schedule performance index) field shows the ratio of work performed to work scheduled (BCWP/BCWS). SPI is often used to estimate the project completion date.
How Calculated
SPI = BCWP / BCWS
An SPI ratio greater than 1 indicates that youre ahead of schedule. Likewise, an SPI ratio less than 1 indicates that youre behind schedule. For example, an SPI of 1.5 means that youve taken only 67% of the planned time to complete a portion of a task in a given time period. An SPI of 0.8 means that youve spent 25% more time on a task than was planned.
CPI (cost performance index) field shows the ratio of budgeted (or baseline) costs of work performed to actual costs of work performed, up to the project status date or todays date. Use quantity instead.
How Calculated CPI is the ratio of BCWP (budgeted cost of work performed) to ACWP (actual cost of work performed):
CPI = BCWP / ACWP
Best Uses This value indicates whether you are over or under budget as of the data date.
What i mean is Schedule Performance / productivity Factor / index (i.e. in terms of manhours). In determining the actual it is = earned manhour / Actual Manhour.
Regards
Member for
22 years 11 months
Member for22 years11 months
Submitted by Bernard Ertl on Sun, 2003-11-16 11:45
This issue was discussed recently in the Progress Measurement Units thread. If you do not find what you are looking for in there, perhaps you could be more specific as to what you are trying to measure?
Member for
16 years 9 monthsRE: SCHEDULE PERFORMANCE FACTOR
Ref. the post that SPI is 1. Yes planningwise but not arithmetically as the formula suggested because how can you have BCWP if the project have not started.
Member for
22 years 11 monthsRE: SCHEDULE PERFORMANCE FACTOR
There are several ways to generate a curve of % complete targets. We graph the cumulative scheduled manhours from ES to EF. Ie. for day 1, total all scheduled manhours on day 1 and divide by the total manhours for the entire schedule. For Day 2, total all manhours for day 2, divide by the total manhours for the entire schedule and add day 1 percentage.
You can also graph the manhours from LS to LF in addition to the above to display a target range for each day (or whatever your reporting period is).
HTH!
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Member for
16 years 9 monthsRE: SCHEDULE PERFORMANCE FACTOR
Sorry to be so contrite! but a baseline plan however good or bad assumes 100% efficiency throughout the life of the programme so whether you look at it weekly, monthly the performance index is constant - but it seems a meaningless question - I must be missing something.
However you can assess the risks associated using various techniques - Three-point-estimating is fairly reliable providing the project is not completely new to the organisation. This should give you the earliest/’mid’/latest dates for the project - I suppose you can then set these up as some sort of PPI.
Member for
16 years 9 monthsRE: SCHEDULE PERFORMANCE FACTOR
erm the projected performance index at the start of a project is always 1.
Member for
22 years 4 monthsRE: SCHEDULE PERFORMANCE FACTOR
Thank you Gentlemen,
But what I want to know is Projected Performance Index from start to finish of the project (i.e. weekly, monthly,etc... as in - projected %).
Member for
16 years 9 monthsRE: SCHEDULE PERFORMANCE FACTOR
Moises,
Planned or Scheduled SPI is meaningless/no use at all at the start of the project because it will be 0. As you project it, it is also 0 because you dont have a numerator(Actual Quantity).
Perhaps what you are asking is the projected %Complete using manhours.
Member for
22 years 11 monthsRE: SCHEDULE PERFORMANCE FACTOR
Moises,
Your last two posts are confusing to me. How can you determine a SPI based upon actual hours before the project starts? Perhaps I am still not understanding what you are trying to do....
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Member for
22 years 3 monthsRE: SCHEDULE PERFORMANCE FACTOR
Please see websit PD-Trak FOR YOUR QUESTION.
PD-Trak™ provides key metrics to determine project, product, and portfolio performance
Member for
22 years 4 monthsRE: SCHEDULE PERFORMANCE FACTOR
Forum Guest, thanks for your reply. But what i want to know is the schedule SPI, which i want to establish before project starts (i.e. weekly , monthly etc basis).
Member for
16 years 9 monthsRE: SCHEDULE PERFORMANCE FACTOR
Moises,
Im not really sure about your question, but the following might be of help.
Using earned value analysis, just change the cost values to quantity values.
The SPI (schedule performance index) field shows the ratio of work performed to work scheduled (BCWP/BCWS). SPI is often used to estimate the project completion date.
How Calculated
SPI = BCWP / BCWS
An SPI ratio greater than 1 indicates that youre ahead of schedule. Likewise, an SPI ratio less than 1 indicates that youre behind schedule. For example, an SPI of 1.5 means that youve taken only 67% of the planned time to complete a portion of a task in a given time period. An SPI of 0.8 means that youve spent 25% more time on a task than was planned.
CPI (cost performance index) field shows the ratio of budgeted (or baseline) costs of work performed to actual costs of work performed, up to the project status date or todays date. Use quantity instead.
How Calculated CPI is the ratio of BCWP (budgeted cost of work performed) to ACWP (actual cost of work performed):
CPI = BCWP / ACWP
Best Uses This value indicates whether you are over or under budget as of the data date.
Member for
22 years 4 monthsRE: SCHEDULE PERFORMANCE FACTOR
Gentlemen,
What i mean is Schedule Performance / productivity Factor / index (i.e. in terms of manhours). In determining the actual it is = earned manhour / Actual Manhour.
Regards
Member for
22 years 11 monthsRE: SCHEDULE PERFORMANCE FACTOR
This issue was discussed recently in the Progress Measurement Units thread. If you do not find what you are looking for in there, perhaps you could be more specific as to what you are trying to measure?
Bernard Ertl