The performance % complete is not equal cost % complete

Y
yahya atef 👤 Member for 9 years 1 month

I make revised plan for my project but there is a problem the performance % complete does not equal the cost % complete ?

 

R
Rodel Marasigan 👤 Member for 19 years 8 months

Performance % Complete:

The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, the 0/100 rule, the 50/50 rule, or other techniques, depending on the method used to calculate the earned-value percent complete for the activity's Work Breakdown Structure (WBS). The Performance % Complete specifies the percentage of the activity's planned value that has been earned so far. On the other hand, the cost % complete is calculated based on the actual costs entered in the Actual Cost field, including labor, non-labor, materials, and expenses. To match it, you can adjust the cost value to align with the earned value.

Forum Sponsor

Top Posters

AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts