The performance % complete is not equal cost % complete

Y
yahya atef 👤 Member for 9 years 2 months

I make revised plan for my project but there is a problem the performance % complete does not equal the cost % complete ?

 

R
Rodel Marasigan 👤 Member for 19 years 8 months

Performance % Complete:

The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, the 0/100 rule, the 50/50 rule, or other techniques, depending on the method used to calculate the earned-value percent complete for the activity's Work Breakdown Structure (WBS). The Performance % Complete specifies the percentage of the activity's planned value that has been earned so far. On the other hand, the cost % complete is calculated based on the actual costs entered in the Actual Cost field, including labor, non-labor, materials, and expenses. To match it, you can adjust the cost value to align with the earned value.

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts