Change in Budgeted Units

Hello Everyone,

 

I exported a schedule, rerouce loaded it and imported it back to the P6.

 

After checking some activity I saw that I for got to add some other resource for the same activity. But when I add this resource through Primavera it changes the existing allocated reource. I do not want that to happen. Please advice me on how to tackle it.

 

Example :

Activity A had a resource at First: Carpenter - 20 Hrs .

 

I missed adding Labor, so when I added it. It distributes the 20 Hrs, Now Carpenter = 10 Hrs, Labor = 10 Hrs

 

Thanks

Jithin

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Jithin,

You need to change the Resource assignment calculation when adding or removing resources. On menu select Edit--> User Preferences. When the pop-up window User Preferences click Calculation tab and select Preserve Units, Duration, .... see below:

Resource-Assignment-Option

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts