Hello Everyone,

 

I exported a schedule, rerouce loaded it and imported it back to the P6.

 

After checking some activity I saw that I for got to add some other resource for the same activity. But when I add this resource through Primavera it changes the existing allocated reource. I do not want that to happen. Please advice me on how to tackle it.

 

Example :

Activity A had a resource at First: Carpenter - 20 Hrs .

 

I missed adding Labor, so when I added it. It distributes the 20 Hrs, Now Carpenter = 10 Hrs, Labor = 10 Hrs

 

Thanks

Jithin

R
Rodel Marasigan 👤 Member for 19 years 8 months

Hi Jithin,

You need to change the Resource assignment calculation when adding or removing resources. On menu select Edit--> User Preferences. When the pop-up window User Preferences click Calculation tab and select Preserve Units, Duration, .... see below:

Resource-Assignment-Option

Forum Sponsor

Top Posters

James Williams
74 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts