Physical % complete for milestone date

Hi Planners

I am updating a schedule and the first activity is start milestone, when I enter the actual start date, the percentage complete does not change to 100% and I tried to fill it manually but it does not work. It works for other activities.

 

Regards,

Muataz

Z
Zoltan Palffy 👤 Member for 16 years 10 months

in the general tab is the % complete type set to physical

did you check the Started box next to the date ?